Chapter 10
Setting Up the System
This chapter describes the system setup work to be done after a FRU is replaced,
added, or removed or after the building block configuration is changed. See this
chapter, as required, after replacing, adding, or removing a FRU.
Preparing Hardware
■
Restoring Setting Information
■
Adding the SPARC M12-2S to a Building Block Configuration
■
Incorporating a FRU Into the System
■
Diagnosing a Replacement FRU
■
Incorporating the SPARC M12-2S or an I/O Device Into the PPAR
■
Incorporating I/O Resources Into a Logical Domain
■
Powering on a Physical Partition
■
Starting the System
■
10.1
Preparing Hardware
This section describes the following procedures required for setting up the hardware.
Installing a Power Cord
■
Securing the Cable Support
■
Installing the Front Cover
■
10.1.1
Installing a Power Cord
If you have removed the power cord from the PSU to perform the maintenance work,
connect the power cord to the PSU and then attach the power cord to the cable
clamp.
1.
Connect the power cord to the PSU.