Chapter 10
Setting Up the System
This chapter describes the system setup work to be done after a FRU is replaced,
added, or removed or after the building block configuration is changed. See this
chapter, as required, after replacing, adding, or removing a FRU.
Preparing Hardware
Restoring Setting Information
Adding the SPARC M12-2S to a Building Block Configuration
Incorporating a FRU Into the System
Diagnosing a Replacement FRU
Incorporating the SPARC M12-2S or an I/O Device Into the PPAR
Incorporating I/O Resources Into a Logical Domain
Powering on a Physical Partition
Starting the System
10.1
Preparing Hardware
This section describes the following procedures required for setting up the hardware.
Installing a Power Cord
Securing the Cable Support
Installing the Front Cover
10.1.1
Installing a Power Cord
If you have removed the power cord from the PSU to perform the maintenance work,
connect the power cord to the PSU and then attach the power cord to the cable
clamp.
1.
Connect the power cord to the PSU.
325