Step 4 Rotate the expansion bolt counterclockwise to remove it together with the spring washer and
flat washer.
Figure A-1 Expansion bolt
(1) M12 bolt
(3) Flat washer
Figure A-2 Drilling a hole and installing an expansion sleeve (unit: mm)
----End
A.3 Installing a Floating Nut
Figure A-3
Issue 01 (2019-03-05)
Put aside the removed expansion bolt for securing the cabinet.
shows how to install a floating nut.