Optional) Installing The Vertical Ground Bar - Huawei FusionModule5000 Series Installation Manual

Smart modular data center single-row aisle containment with 2000 mm high cabinets, ecc800
Hide thumbs Also See for FusionModule5000 Series:
Table of Contents

Advertisement

FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
Figure 5-12 Installing a ground bar
----End

5.4.3 (Optional) Installing the Vertical Ground Bar

Context
The BOM number for the vertical ground bar is 21241363.
Procedure
Step 1 Open the rear cabinet door, and secure the ground bar to the right rack rail by installing four
M4 screws respectively at the 04 U, 14 U, 29 U, and 39 U positions. Note that a screw should
be secured to the middle tapped hole of each U.
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
5 Installing the Cabinet
73

Advertisement

Table of Contents
loading

Table of Contents