FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
Figure 6-8 300 mm wide flat skylight
(1) Skylight connective plate
6.2.2 Securing Skylights
Context
Install skylights one by one from one end of the smart module based on the onsite engineering
layout diagram.
The recommended skylight layout is as follows:
Procedure
Step 1 Keep the skylight connective plates flush with the end plane of the cabinet upper sealing plate
and the end plane of the enclosure plate in the aisle containment. Use four M8x20 screws to
partially secure the two skylight connective plates to the correct mounting holes, as shown by
(1) in
Issue 01 (2019-03-05)
The 300 mm wide flat skylight is used with a 300 mm wide air conditioner.
Install control skylights at the outermost positions at both ends of the aisle.
Deploy rotating skylights and flat skylights alternately.
Preferentially deploy rotating skylights beside control skylights.
Figure
6-9.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
6 Installing the Contained Aisles
(2) Flat skylight panel
83