FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
Figure 8-4 Rotating the vertical plate by 90 degrees
Step 3 Install the other vertical plate into the mounting hole in the second row counting from the
front door to the rear door in the same way. Install one M5x10 tapping screw inside each of
the two vertical plates to ensure equipotential bonding with the cabinet, as shown in
5.
Figure 8-5 Installing the other vertical plate
Step 4 Press a supporting plate along the two vertical plates down to the place between the four
clasps and the cable bridge, as shown in
into the clasps.
When installing the supporting plate, do not remove the grommet strip on the U-shaped trough.
Issue 01 (2019-03-05)
Figure
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
8 (Optional) Installing Cable Troughs
8-6. Ensure that the supporting plate is fully
Figure 8-
107