Step 1 Assemble cable trays. Place four cable tray supports at the coated positions on the cable trays.
Secure each support to the cable trays using four M8 screws.
Figure A-30 Assembling cable trays
Issue 01 (2019-03-05)
Figure A-29 Layered installation