persons carry the equipment. Force-bearing area is shown in
it to prevent tilting. Then install the side panel.
Exercise caution when moving the cabinet to prevent falling down.
Figure 4-36 Transport
----End

4.4 Adjusting the Baffle Plate for the Air Conditioner

Context
Perform the following procedure to change the position of the baffle plate if required.
Procedure
Step 1 Loosen the two screws shown by (1) in
Issue 01 (2019-03-05)
Figure
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
4 Hardware Installation Preparations
Figure
4-36. The other two hold
4-37.