Figure 9-56 Securing a baffle plate
----End

9.9 (Optional) Installing a Smart ETH Gateway

Prerequisites
Context
Table 9-4 Scenario 1
Scenario
Issue 01 (2019-03-05)
You have prepared a smart ETH gateway and installation accessories such as the guide
rail (delivered with the smart ETH gateway) and screws.
The number of smart ETH gateways to be installed and their installation positions have
been specified.
Components marked in the same background color should be connected to the same smart ETH
gateway.
No rack environment unit deployed
Module length ≤ 7 m; number of air
conditioners ≤ 4
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
9 Installing Monitoring Devices
Rules for Deploying Smart ETH
Gateways
Deploy 2 PCS for each end cabinet in the
smart module, not for other cabinets. A total
of 4 PCS should be deployed, as shown in
Figure
9-57.