Huawei FusionModule5000 Series Installation Manual page 87

Smart modular data center single-row aisle containment with 2000 mm high cabinets, ecc800
Hide thumbs Also See for FusionModule5000 Series:
Table of Contents

Advertisement

FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
Figure 6-1 Installing sealing plates
Step 2 Place sealing plates.
When placing a sealing plate, keep the smooth plane facing the outside of the contained
aisle.
Keep the end with rivet nuts facing upward and the end with holes facing downward.
Ensure that the side of cabinets is on the same plane as the side of the sealing plates.
Step 3 (Optional) If the floor is uneven, add a 1.0 mm or 2.0 mm high pad under the lower sealing
plate, as shown by (1) in
Step 4 Secure the sealing plates to the floor using ST4.8x25 tapping screws or DKBA44091028
plastic expansion bolts and gaskets, as shown by (2) in
Issue 01 (2019-03-05)
Figure
6-1.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
6 Installing the Contained Aisles
Figure
6-1.
78