FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
1.
Trim the PC plate using a hook knife and place it on the adjustable skylight.
To ensure a neat section after trimming, trim the PC plate using the aisle check tool in the Num. 0
packing box.
2.
Mark a line on the column where the PC plate closely attaches to the column using a
marker.
3.
Move the PC plate. Drill holes on the column and secure the L-shaped mounting
brackets to the column using plastic expansion bolts.
Figure A-26 Securing L-shaped mounting brackets
(1) Column
Step 4 Install PC plates.
1.
Pave PC plates on the adjustable skylight.
2.
Secure PC plate fasteners to PC plate supports.