Procedure
Step 1 Trim the PC plate to an appropriate size using a hook knife.
Figure A-21 Trimming a PC plate
(1) PC plate
Step 2 Attach the PC plate fastener to the trimmed PC plate.
Figure A-22 Attaching a PC plate fastener to a trimmed PC plate
Step 3 Secure the PC plate fastener and the trimmed PC plate to the skylight connective plate.
Issue 01 (2019-03-05)
To ensure a neat section after trimming, trim the PC plate using the aisle check tool in the Num. 0
packing box.