Huawei FusionModule5000 Series Installation Manual page 200

Smart modular data center single-row aisle containment with 2000 mm high cabinets, ecc800
Hide thumbs Also See for FusionModule5000 Series:
Table of Contents

Advertisement

FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
Figure 12-30 Connecting power cables to the circuit breaker
6.
(Optional) If the intelligent battery monitoring system is not deployed, use a 04080376
cable to connect the J1 port on the battery control board (BIB) to the corresponding port
on the UPS. Alternatively, use a 04080377 cable for cascading and use a 04080376 cable
for connecting to the corresponding port on the UPS.
Figure 12-31 Connecting monitoring cables for the circuit breaker
7.
(Optional) If the intelligent battery monitoring system is deployed, for details about how
to install, connect cables, and power on the BIM and CIM, see iBAT 2.0-CIM01C2 User
Manual (Click Download.).
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
12 Cable Routing