Huawei FusionModule5000 Series Installation Manual page 193

Smart modular data center single-row aisle containment with 2000 mm high cabinets, ecc800
Hide thumbs Also See for FusionModule5000 Series:
Table of Contents

Advertisement

FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
Figure 12-19 M-type grounding
S-type Grounding
Figure 12-20
Issue 01 (2019-03-05)
This solution is applicable only to the PDC scenario. You need to customize it if you want to use this
solution.
shows the cabinet ground points. Connect cabinet ground cables as follows:
Connect the cabinet ground bar or ground point to the branch ground bar of the battery
cabinet or IT cabinet near the PDC, and then connect the branch ground bar to the
general ground bar inside the PDC.
If no branch ground bar is installed, connect the cabinet ground copper bar or ground
point directly to the general ground bar inside the PDC.