Figure 4-19 800 mm wide fixed base

4.1.2.5 Securing Bases

Prerequisites
Cabinet bases are placed on a concrete floor as planned.
Context
Table 4-1
Table 4-1 Securing bases
Support
600 mm wide fixed base
800 mm wide fixed base
300 mm wide fixed base
600 mm adjustable base
Procedure
Step 1 (Optional) If the ground is not flat, place a washer (0.5 mm, 1.0 mm, or 2.0 mm high) under
the base.
Step 2 Mark holes for installing expansion bolts on the concrete floor by using a marker.
Step 3 Remove the base, and drill holes in the marks by using a hammer drill with a Ф16 drill bit.
The hole depth must range from 52 mm to 60 mm.
Step 4 Use a vacuum cleaner to clean up dust in or around the holes, as shown in
Issue 01 (2019-03-05)
describes how to secure bases.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
4 Hardware Installation Preparations
Securing Method
Drill holes at positions for installing the four
supports of the base, and secure the base to
the concrete floor using four expansion
bolts.
Drill holes at positions for installing the six
supports of the base, and secure the base to
the concrete floor using six expansion bolts.