FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
Figure 9-46 Assembling a pad power connector holder (BOM number: 14190892)
Figure 9-47 Assembling a pad power connector holder (BOM number: 14190242)
Step 2 Connect cables from the power connector to the AC actuator, and route the cables, as shown
in the following figure.
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
9 Installing Monitoring Devices