Figure 5-4 Using a laser locator for positioning
(1) Marking-off template
Step 4 Use a measuring tape to measure the aisle distance and mark the position for the end cabinet
in the other row in the same way.
Step 5 (Optional) Drill holes into the marked hole positions and install expansion bolts.
----End

5.3 Installing Cabinets (Without Bases)

Procedure
Step 1 Place end cabinets in the marked positions, as shown in
Issue 01 (2019-03-05)
When laying out the marking-off template, verify that the cabinet front door faces a cold
aisle or outside of the module in the case of a hot aisle.
If there is no need to secure the cabinet to the floor, mark only the outline of the marking-
off template.
The M12 expansion bolts should be supplied by the customer. The M12 bolt must be at least 80 mm
long for a 2000 mm high cabinet.
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
(2) Contained aisle
Figure
5-5.