Step 4 Remove the hinges and connecting plates from the PDC rear door, as shown in
Put aside the hinges and connecting plates as they are needed in follow-up installation
processes.
Figure 4-44 Removing the PDC rear door mounting kit
Step 5 Move the tail frame installed with accessories and upper sealing plates to the cabinet rear
door, and adjust the anchor bolts of the tail frame so that the fail frame top is flush with the
cabinet top.
Step 6 Secure the tail frame to the PDC using eight M5 tapping screws, as shown in
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
4 Hardware Installation Preparations
Figure
Figure
4-44.
4-45.
59

Advertisement

Table of Contents
loading

Table of Contents