First Commissioning With The Aop30 - Siemens SINAMICS G130 Operating Instructions Manual

Converter built-in units 75 kw-800 kw
Hide thumbs Also See for SINAMICS G130:
Table of Contents

Advertisement

5.5

First commissioning with the AOP30

5.5.1
First commissioning
Start screen
When the system is switched on for the first time, the Control Unit is initialized automatically.
The following screen is displayed:
Figure 5-39
When the system boots up, the parameter descriptions are loaded into the operating field
from the CompactFlash card.
Figure 5-40
Inverter chassis units
Operating Instructions, 07/2016, A5E00331449A
Initial screen
Load the parameter descriptions while booting up the system
5.5 First commissioning with the AOP30
Commissioning
171