Commissioning of an induction motor
The steps described below also apply to commissioning an induction motor.
When commissioning a permanent-magnet synchronous motor, there are a few special
conditions that apply, which are detailed in a separate chapter (see "Setpoint channel and
closed-loop control / permanent-magnet synchronous motors").
⇒ Click Continue >
Configuring the motor – Entering motor data
Figure 5-20
⇒ Enter the motor data (see motor rating plate).
⇒ Activate Enter optional motor data if necessary.
⇒ Activate Enter optional equivalent circuit diagram data if necessary.
Inverter chassis units
Operating Instructions, 07/2016, A5E00331449A
Configuring the motor – Entering motor data
5.3 Procedure for commissioning via STARTER