16. Screw the retaining nut onto the AC power cord to secure it to the metal wiring compartment.
17. Using a number 2 Phillips (+) screwdriver, tighten the four captive screws on the metal AC wiring
compartment.
18. Verify that the AC power cord does not touch or block access to router components, and that it does
not drape where people could trip on it.
19. Remove the ESD grounding strap from the ESD points on the chassis. Connect the strap to an approved
site ESD grounding point. See the instructions for your site.
20. Connect the AC power cord plug to the power source.
21. Switch on the customer-site circuit breakers to provide voltage on the AC power cord.
22. Remove the ESD grounding strap from the approved site ESD grounding point. See the instructions
for your site. Reconnect the strap to one of the ESD points on the chassis.
23. Verify that the LED on the PDM faceplate is lit steadily, indicating that the AC terminal block is receiving
power.
Installing an MX2000 Router Three-Phase Wye AC Power Distribution
Module
Each three-phase wye AC PDM weighs approximately 12 lb (5.44 kg). To install a three-phase wye AC
PDM:
WARNING:
from the AC circuit. To ensure that all power is off, locate the circuit breaker on the
panel board that services the AC circuit, switch the circuit breaker to the off position,
and tape the switch handle of the circuit breaker in the off position.
Before performing AC power procedures, ensure that power is removed