Figure 4-5. Anchoring On Raised Floor Over Concrete Slab - Tekelec 1100 Hardware Manual

Application server
Hide thumbs Also See for 1100:
Table of Contents

Advertisement

7.
Insert each threaded rod/anchor assembly into its hole, with the cone nut at
the bottom, and tighten with a 3/4 inch (19mm) wrench until the top nut of
the torque nut breaks free (this nut is called the twist-off nut in Figure 4-4 on
page 4-10).

Figure 4-5. Anchoring on Raised Floor Over Concrete Slab

Large washer
Small washer
Nut
8.
At the top end of each threaded rod, thread on a 5/8 inch nut until it is below
the level where the floor tile will meet the threaded rod.
9.
On top of the 5/8 inch nut, drop a small steel washer and then a large steel
washer.
10.
Return tiles to their original positions, fitting the anchor holes in the tiles over
the threaded rod assemblies.
11.
Lay the isolator pad on the raised floor with the holes in the isolator pad
aligned over the threaded rod assemblies.
12.
Roll the frame (still on the dolly) into position above the isolator pad.
4-12
Preliminary
Frame
Finger tighten nuts above
raised floor before tightening
nuts below raised floor
Flat washers
and nuts
How to Install a T1100 AS Frame
side
Locking nut
Washers
Holddown plate
Isolator pad
Raised floor
Concrete floor
Anchor assembly
with threaded rod
910-2969-001 Revision H, February 2007
04_raised_floor_threaded-rod

Advertisement

Table of Contents
loading

Table of Contents