Installation tests
............................................................................................................................................................................................................................................................
OC-48 facility loopback testing
Facility Loopback testing allows the installer to verify cabling to the OC-48 equipment.
This test is only required if the Alcatel-Lucent 1665 DMX shelf is connected to OC-48
equipment. If the shelf is NOT connected to OC-48 equipment, skip this section and
continue to the next chapter.
Note:
necessary for the testing.
The Function unit slot under test must contain an OC-48 (LNW31 or LNW402) circuit
pack in order to perform this test.
........................................................................................................................................................................................................................
1
Log on to the Alcatel-Lucent 1665 DMX shelf using the CIT software as described in the
"Use of WaveStar
........................................................................................................................................................................................................................
2
Select Configuration > Cross-Connections...
........................................................................................................................................................................................................................
3
Use the Cross-Connection Wizard to enter a new cross-connection at the STS48 rate,
UPSR Ring Add/Drop, between m1-1-1 and fn-1-1 (fn will be a,b,c,d or g depending on
the slot where the OC-48 CP is located).
This command creates a cross-connect to map the first STS-48 of an OC-48 circuit pack to
the first STS-48 of the Main OLIUs.
........................................................................................................................................................................................................................
4
Verify transmission at the patch panel. There should be no alarms at the test set.
........................................................................................................................................................................................................................
5
Select Configuration > Cross-Connections...
........................................................................................................................................................................................................................
6
Use the Cross-Connection Wizard to Delete leg(s) of an existing cross-connection
associated with CP main-1, Port 1 (the OC-48 cross-connection).
........................................................................................................................................................................................................................
7
Verify loss of transmission at the patch panel. This should be evident by a SONET alarm
and a loss of pattern alarm.
........................................................................................................................................................................................................................
8
Select Fault > Analysis > Loopback...
............................................................................................................................................................................................................................................................
6 - 4 6
An optical test set with the capability to transmit OC-48 SONET levels are
®
CIT software" (p.
5-6).
OC-48 (low-speed) testing
Alcatel-Lucent 1665 DMX R9.0