FusionModule2000-S Smart Modular Data Center
User Manual
Figure 3-21 Removing M8 screws
Step 2 Open the cabinet rear door, install the horizontal ground bar on the topmost
position on the outside of the mounting bar, and secure the ground bar using the
M8 screws removed earlier.
Figure 3-22 Installing a horizontal ground bar
----End

3.5.1.4 (Optional) Installing a Vertical Ground Bar

Context
Install the vertical ground bar in the IT cabinet closest to the PDF.
Preparations
Tool: Phillips screwdriver
Material: vertical ground bar
Procedure
Step 1 Open the cabinet rear door and use four M4 screws to secure the vertical ground
bar to the right mounting bar.
Issue 03 (2021-07-15)
Copyright © Huawei Technologies Co., Ltd.
3 Hardware Installation