LUNA2000-200KWH-2H1 Smart String ESS
User Manual
7.4.3 Installing the Smart Rack Controller
Prerequisites
Unpack and check the rack controller delivered to the site to ensure that it is
intact.
Procedure
Step 1 Remove the decorative cover and maintenance compartment cover from the rack
controller.
Figure 7-23 Removing covers
Step 2 Install short-circuiting copper bars that are delivered with the product.
Figure 7-24 Installing short-circuiting copper bars
Step 3 Install the maintenance compartment cover and the decorative cover to the rack
controller.