Upgrading R5si/R6si to an Avaya DEFINITY Server R
EPN running Avaya Communication Manager
Shut Down DEFINITY AUDIX System
1. If a DEFINITY AUDIX System resides in the system to be upgraded, shut
down the AUDIX assembly and allow the disk to completely spin down.
Refer to the
chapter.
!
WARNING:
Neglecting to shut down an AUDIX assembly before powering down
the system cabinet where it resides can damage the AUDIX disk.
2. Unseat the AUDIX assembly from its backplane connectors.
Power Down Existing System
!
CAUTION:
Powering down the PPN causes important system data, such as BCMS
data, records of queued ACD calls, Automatic Wakeup requests, and Do Not
Disturb requests to be lost. Refer to Maintenance for Avaya DEFINITY
Server SI, for information about preparing the system for a power down.
1. At each PPN cabinet power supply, set the main circuit breaker to OFF.
2. At each EPN cabinet power supply, set the main circuit breaker to OFF.
4-18
Issue 7 November 2003
''DEFINITY AUDIX Power Procedures''
at the end of this
555-233-115
Need help?
Do you have a question about the DEFINITY Server R and is the answer not in the manual?