Commissioning
5.1

Chapter content

This section provides information on the following:
● An overview of the operator panel functions
● Initial commissioning of the cabinet unit (initialization) with STARTER and AOP30
– Entering the motor data (drive commissioning)
– Entering the most important parameters (basic commissioning), concluding with motor
● Data backup
● Parameter reset to factory settings
Important information prior to commissioning
The cabinet unit offers a varying number of internal signal interconnections depending on the
delivery condition and the options installed. For the converter control to be able to process
the signals correctly, several software settings must be made.