Installing the MX2020 Lower Cable Manager

314

Figure 161: Installing the Air Baffle

Maintaining the MX2020 Air Baffle on page 344
Removing the MX2020 Air Baffle on page 475
NOTE:
To accommodate additional clearance, you may order an extended
lower cable manager from Juniper Networks.
To install the lower cable manager (see
Position the lower cable manager on the studs on the lower front of the chassis, just
1.
below the MPCs.
Insert the screws into the corners in the lower cable manager onto the studs on the
2.
chassis.
Using a Phillips (+) screwdriver (number 1 or 2), tighten the mounting screws securely.
3.
Replace the cable manager cover, and secure it with the two captive screws.
4.
Figure 162 on page
315):