Step 1 Wear an ESD wrist strap or ESD gloves. For details, see
Step 2 Take out the front I/O module from the ESD bag and install the internal
components, such as the RAID controller card, supercapacitor, hard disk indicator
panel, and hard disk backplane.
Step 3 Hold the ejector levers of the front I/O module and push the module steadily into
the cabinet. See step (1) in
Step 4 Lower the ejector levers on both sides of the front I/O module. See step (2) in
Figure
Issue 30 (2019-12-19)
You have powered off the RH8100 V3. For details, see
RH8100
V3. Then you have removed all power cables from the server.
You have installed the RAID controller card on the front I/O module. For
details, see
5.6.6 Installing a RAID Controller
You have installed the supercapacitor on the front I/O module. For details, see
5.6.8 Installing a
Supercapacitor.
You have installed the hard disk indicator panel on the front I/O module. For
details, see
5.6.10 Installing a Hard Disk Indicator
You have installed the hard disk backplane on the front I/O module. For
details, see
5.6.12 Installing a Hard Disk
You have obtained the cabinet number and chassis number of the RH8100 V3.
You have located the RH8100 V3 based on the preceding information, and
labeled its panel to prevent misoperations.
You have determined the position on the RH8100 V3 for installing a front I/O
module.
ESD gloves
Packaging materials, for example, an ESD bag
5-64.
Copyright © Huawei Technologies Co., Ltd.
5 Removing and Installing Parts of the RH8100 V3
Backplane.
Figure
5-64.
6.2 Powering Off the
Card.
Panel.