Checking The Grounding - Siemens HiPath 3000 Service Manual

Hide thumbs Also See for HiPath 3000:
Table of Contents

Advertisement

inst_h3.fm
Installing HiPath 3000
Installing HiPath 3800
4.2.3.5

Checking the Grounding

Procedure
Perform the tests in the table below to ensure that the system is properly grounded before star-
tup.
Step
1.
Check the ohmic resistance of the ground connection to
the system:
Perform measurement between the PE (protective
earth) on a socket in the internal installation (at the sys-
tem's installation site) and HiPath 3800.
Prerequisites:
HiPath 3800 is not yet connected to the low-voltage
network via the power cable.
The system's separate grounding is connected.
2.
Check the ohmic resistance between the individual sys-
tem parts (basic cabinet, expansion cabinet, main distri-
bution frame).
Prerequisite:
HiPath 3800 is not yet connected to the low-voltage net-
work via the power cable.
4-20
Activity
HiPath 3000 V5.0, HiPath 5000 V5.0, Service Manual
Target
< 10 ohms
< 1 ohm
P31003-H3550-S403-4-7620, 02/05

Advertisement

Table of Contents
loading

This manual is also suitable for:

Hipath 5000

Table of Contents