Reinstalling the T1600 FPCs

Copyright © 2010, Juniper Networks, Inc.
To reinstall FPCs (see Figure 80 on page 122):
Attach an electrostatic discharge (ESD) grounding strap to your bare wrist, and connect
1.
the strap to an approved site ESD grounding point. See the instructions for your site.
Using the list you created when you removed the FPCs, locate the slot in the FPC card
2.
cage in which you plan to install the FPC.
Lift the FPC into place and carefully align first the bottom, then the top of the FPC
3.
with the guides inside the card cage. Be sure the FPC is right-side up, with the
components on the right of the FPC.
CAUTION: When the FPC is out of the chassis, do not hold it by the ejector
handles, bus bars, or edge connectors. They cannot support its weight.
Slide the FPC all the way into the card cage until you feel resistance.
4.
Starting with the ejector handles on the FPC faceplate nearly horizontal, simultaneously
5.
turn both ejector handles clockwise to seat the FPC.
If you are installing a Type 2 FPC or Type 3 FPC, tighten the screws inside the ejector
6.
handles to secure the FPC. Do not overtighten them.
Repeat the procedure to reinstall each remaining FPC.