Site Preparation Checklist for an EX6200 Switch

Table 41: Site Preparation Checklist

Item or Task
Environment
Verify that environmental factors such as
temperature and humidity do not exceed switch
tolerances.
Power
Measure distance between external power
sources and switch installation site.
Copyright © 2014, Juniper Networks, Inc.
Site Preparation Checklist for an EX6200 Switch on page 89
General Site Guidelines on page 91
Site Electrical Wiring Guidelines on page 91
Environmental Requirements and Specifications for EX Series Switches on page 93
The checklist in
Table 41 on page 89
a site for installing an EX6200 switch.
For More Information
"Environmental Requirements and
Specifications for EX Series Switches"
on page 93
summarizes the tasks you need to perform to prepare