Create PVC 0/35 and Apply the Data IPQoS Profile
8
In the navigation panel, click Port > PVC to open the PVC Setup screen.
8a
Select the slot where the line card is installed and port 2. Click Load.
8b
Figure 256 Data PVC Setup Screen PVC 0/35
In the VPI/VCI fields, enter "0" and "35".
8c
Enter 3 in the PVID field.
8d
In the Profile field, select "Data".
8e
In the Priority field, select 0.
8f
Click Apply.
8g
Save the Settings
9
In the navigation panel, click Config Save > Config Save to open the VDSL Port Setup
9a
screen.
Figure 257 Config Save Screen
Management Switch Card User's Guide
Chapter 11 Profile Screens
395