5-146 Emergency power conservation recovery procedures
Emergency power conservation
Emergency shutdown of one LIM unit on each LPP
3
4
297-8021-545 Standard 14.02 May 2001
WARNING
Possible loss of service
Make sure that the mate LIM unit is in service before you
busy the LIM unit that you will power down. Failure to
follow this procedure can isolate nodes on link interface
shelves (LIS) 1, 2, and 3.
To access the F-bus level of the MAP display, type
>FBUS
and press the Enter key.
Example of a MAP display:
Tap: 0
FBus0: InSv
.... .... .... ....
FBus1: InSv
.... .... .... ....
WARNING
Possible loss of service
Make sure that the mate F-bus and its equipped taps are in
service. Complete this procedure before you busy the F-bus
that associates with the LIM unit that you will power down.
Failure to follow this procedure will isolate application
specific units (ASU) on LIS 1, 2, and 3.
To manually busy the F-bus associated with the LIM unit that you will power
down, type
>BSY
FBUS
fbus_no
and press the Enter key.
where
fbus_no
is the number of the F-bus (0 or 1)