Who may perform the acceptance test of the converter?
Personnel from the machine manufacturer, who, on account of their technical qualifications
and knowledge of the safety functions, are in a position to perform the acceptance test in the
correct manner are authorized to perform the acceptance testing of the converter.
Wizard for the acceptance test
The "Startdrive Advanced" commissioning tool (requires an appropriate license) includes a
wizard for the acceptance test of the safety functions integrated in the drive.
"Startdrive Advanced" guides you through the acceptance test, generates the appropriate
traces to analyze the machine response – and generates an acceptance report as Excel file.
Further information is provided on the Internet:
(https://support.industry.siemens.com/cs/ww/en/view/109771710) (Startdrive, system
requirements and download)
Reduced acceptance test after function expansions
A full acceptance test is necessary only after first commissioning. A reduced acceptance test
is sufficient when safety functions are expanded.
Measure
Functional expansion of the ma-
chine (additional drive).
Transfer of converter settings to
other identical machines by means
of series commissioning.
SINAMICS G115D distributed drive
Operating Instructions, 12/2020, FW V4.7 SP13, A5E48681219B-002
Startdrive, system requirements and download
6.14 Safe Torque Off (STO) safety function
Acceptance test
Acceptance test
Yes.
Only check the safety func-
tions of the new drive.
No.
Only check the control of
all of the safety functions.
Advanced commissioning
Documentation
•
Supplement machine overview
•
Supplement converter data
•
Add function table
•
Log the new checksums
•
Countersignature
•
Add machine description
•
Check checksums
•
Check firmware versions