Installation Of Mguard Blade - Innominate mGuard Reference Manual

Table of Contents

Advertisement

mGuard blade
Power supply switch P1 and P2
Power supply connection P1 and P2
184
Innominate Security Technologies
10.3

Installation of mGuard blade

mGuard bladebase
Figure 10-3
Installation of mGuard blade
NOTE: Always ensure sufficient air circulation for the BladePack.
If several BladePacks are stacked, one or more inches of fan trays must be installed to
discharge the accumulated warm air.
Installation of mGuard bladebase
Install the mGuard bladebase in the rack, e.g., close to the patch field.
Fit the two power supplies and the control unit with the handling plates "P1", "P2", and
"Ctrl" on the front from left to right.
Connect both power supplies on the back of the mGuard bladebase with 100 V or
220/240 V.
Switch on both power supplies.
The LEDs on the front of the power supplies are now green.
Installation of mGuard blade
The mGuard bladebase does not have to be switched off when installing or removing an
mGuard blade.
Loosen the top and bottom screw on the faceplate or on the mGuard blade to be re-
placed.
Remove the faceplate or pull out the old mGuard blade.
Insert the new mGuard blade and PCB into the plastic guides and push it completely
into the mGuard bladebase.
Secure the mGuard blade by tightening the screws slightly.
Replace the empty handling plate with the suitable number from the mGuard bladebase
accessories or replace it with the plate from the old mGuard blade. To do this, pull or
push the plate sideways.
mGuard blade
mGuard blade 1 to 12
Control unit (CTRL)
Power supply P1 and P2
Handling plates
Screws
I15007_en_02