MG 1000B platform hardware installation
position #1, all 96 channels are available. If there is a 32 port DB installed in daughterboard
position #1, all 32 channels are available.
The following procedure describes how to install a DSP Daughterboard on an card.
Figure 29: DSP Daughterboard
Installing a DSP Daughterboard
1. Place the on a safe ESD surface.
2. Place the DSP Daughterboard in either Daughterboard position 1, position 2, or both
depending on how the Daughterboard will be configured from a TN perspective.
3. Ensure the DSP Daughterboard is securely attached to the (using supplied screws).

Gateway Controller installation

Reuse the existing 3-port SDI cable (NTBK48) for installation of a Gateway Controller in a MG
1000E cabinet or chassis. Connect it to the SDI port on the cabinet and the COM RS232 port on the
chassis.
Figure 30: NTBK48 connectors
Branch Office Installation and Commissioning
122
on page 123 illustrates the two connectors.