Avaya 1000 Installation And Commissioning Manual page 97

Branch office
Hide thumbs Also See for 1000:
Table of Contents

Advertisement

VxWorks-based Branch Office systems do not require a CP PM card BIOS upgrade.
Upgrading the Main Office to Communication Server 1000 Release 7.6
1. Upgrade the main office software to Communication Server 1000 Release 7.6 through the
Deployment Manager; see Avaya Linux Platform Base and Applications Installation and
Commissioning, NN43001-315.
Important:
Signaling Server software is available on the Linux platform only.
2. Upgrade the main office Voice Gateway Media Cards to Communication Server 1000
Release 7.6.
3. Upgrade the MG 1000B Voice Gateway Media Cards to Communication Server 1000
Release 7.6.
Upgrading the Branch Office to Communication Server 1000 7.6
1. Upgrade the Small System to Communication Server 1000 Release 7.6.
2. Upgrade the Branch Office software to Communication Server 1000 Release 7.6 through the
Deployment Manager; see Avaya Linux Platform Base and Applications Installation and
Commissioning, NN43001-315.
Important:
Signaling Server software is available on the Linux platform only.
June 2014
Upgrading to Communication Server 1000 Release 7.6
Branch Office Installation and Commissioning
Comments? infodev@avaya.com
97