1. If the hydraulic fittings were removed from the chute cleaning cylinder,
lubricate new O-rings with clean hydraulic fluid, position the O-rings to the
fittings, and install the fittings into the chute cleaning cylinder ports; refer to
Installing the Hydraulic Fittings (page
2. Position the chute cleaning cylinder onto the lever (4).
Note: The chute cleaning cylinder barrel end should be towards right side
of the machine.
3. Slide and secure the chute cleaning cylinder (6) with the pins (5) and split
pins (7).
4. Remove the caps and plugs that were installed to the hydraulic hoses and
fittings during the removal process.
5. Put a coating of clean hydraulic fluid on new fitting O-rings, install the O-rings,
and connect the hydraulic hoses to the fittings on the chute cleaning cylinder.
Tighten the hose connections; refer to
Tubes (page
5–8).
6. After you complete the assembly, ensure that the hydraulic hoses and
fittings do not contact anything to the cutting deck. Also, check for any
hydraulic-fluid leaks.
7. Check the hydraulic-fluid level in the hydraulic tank and add correct quantity
of fluid if necessary; refer to the Operator's Manual.
8. Operate the machine functions slowly until air is out of system; refer to
Charging the Hydraulic System (page
9. Start the engine, check for hydraulic-fluid leaks, repair any leaks as
necessary, and fill the hydraulic tank with the correct quantity of new
hydraulic fluid.
5–10).
Installing the Hydraulic Hoses and
5–72).
Page 5–129
Hydraulic System: Service and Repairs

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

3105031050te

Table of Contents