Preparing the instrument for work performed on its
source
Warning:
source (for example, when changing the probe, installing or removing
the corona pin, operating the source isolation valve, and when
maintaining the source).
To prepare the instrument
1.
In the Instrument Console, click Stop Flow
column flow is required, divert the LC flow to waste as follows:
a.
In the Instrument Console system tree, expand SYNAPT G2
Detector, Interactive Fluidics.
b.
Click Control
c.
Select Waste as the flow state.
2.
In the Instrument Console, click Standby
3.
Set the source temperature to 30 °C.
4.
Wait 30 minutes to allow the desolvation gas flow to cool the probe and
source.
5.
In the Instrument Console, ensure that the API desolvation gas flow is
stopped.
Follow the procedure described below before working on the
.