4-6
2.2.2

Order of Installing Extension Blades

The order in which the station blades (GCD-8DLCA with GPZ-8DLCB,
GCD-16DLCA, GCD-4LCF/G, and GCD-8LCF/G with GPZ-8LCF/G) are
physically inserted determines the numbering plan.
CAUTION
For example, when a digital station blade (GCD-16DLCA) is in Slot 1 (ext.
200~215) and three additional digital station blades are installed in the
following order, the numbering plan below in
Installation Order Example

Table 4-1 Extension Blade Installation Order Example

Order of
Installation
1
2
3
4
After the initial powering up of the system, subsequent powering up or reset
does not change the slot identification. Program 90-05 must be performed
to change the slot identification.
Adding any daughter board to increase the available ports or go to a higher
capacity blade (e.g., GCD-16DLCA) may require that the slot be deleted in
programming and the blade reinstalled. In the following example, to add a
daughter board to slot 2, the blade must be removed, deleted in Program
90-05-01 or through WebPro Blade Configuration, then reinstalled with the
daughter board attached, otherwise the additional ports are not recognized.
This however, uses new ports for the combined blade – the initial ports
(ports 17~24 using the example below) are not used.
To avoid unexpected extension/trunk numbering if the VoIP or
Voice Mail daughter board registers with the system first, install
these boards after the other extension and trunk blades are
installed.
applies.
Blade Slot
Blade
Number
1
GCD-16DLCA
2
GCD-16DLCA
4
GCD-8DLCA
GPZ-8DLCB
3
GCD-8DLCA
Issue 2.0
Table 4-1 Extension Blade
Extension
Numbers
101~116
117~132
133~148
149~156
Installing the SV9100 Blades