2.7

Performing the commissioning

2.7
Performing the commissioning
Begin the commissioning after you have completed the preparations.
1
2
3
4
Figure 8:
Acknowledging
5
warnings/errors
NOTE
Any queued error messages may result from the as yet incomplete parameter setting.
These errors cannot be acknowledged.
26
Parameter manual b maXX BM3000
Document no.: 5.12001.07
of 820
Connect the power supplies to the b maXX
(main power supply + control voltage).
The device then starts up.
Establish communication as described in
Start the ProDrive program (if it is not already running).
Then click on auf "Drive Manager" in ProDrive
ProDrive: Navigation Drive manager
"Acknowledge" any warnings/errors that may be present in the "Drive manager" win-
dow (press the "Reset errors" button several times if necessary).
®
ZPreparations–
on page 18.