Maintenance; Figure 20: Jcs 1200 Chassis Dimensions And Clearance Requirements - Juniper JCS 1200 Hardware Manual

Juniper control system platform
Hide thumbs Also See for JCS 1200:
Table of Contents

Advertisement

Juniper Control System (JCS) 1200 Platform Hardware Guide
JCS 1200 Clearance Requirements for Airflow and Hardware Maintenance
When planning the installation site, allow sufficient clearance around the rack (see
Figure 20 on page 38):

Figure 20: JCS 1200 Chassis Dimensions and Clearance Requirements

Related Topics
38
JCS 1200 Clearance Requirements for Airflow and Hardware Maintenance
JCS 1200 Rack Size and Strength on page 36
JCS 1200 Clearance Requirements for Airflow and Hardware
Maintenance on page 38
For the cooling system to function properly, the airflow around the chassis must
be unrestricted.
For service personnel to remove and install hardware components, there must
be adequate space at the front and back of the platform. Allow at least
30 in. (72.6 cm) in front of the rack and 24 in. (61.0 cm) behind the rack.
Airflow vents provided along the sides of the chassis must remain open and
uncovered for proper cooling.
Overview of Preparing the Site for JCS 1200 Platform Installation on page 33
Site Preparation Checklist for the JCS 1200 Platform on page 33
Rack-Mounting Requirements and Warnings for the JCS 1200 Platform on page 156
JCS 1200 Rack Size and Strength on page 36