Siemens SIMATIC BATCH Operating Manual page 509

Process control system pcs 7
Table of Contents

Advertisement

Result: The synchronization point is displayed as a single line. ROPs/NOPs in the sequence
following this are started immediately (without waiting for synchronization).
Example of synchronization (non-blocking)
The non-blocking position below "Material entry 10" means
● that ROP 20 is processed further by RUP "Dosing setpoint" Immediately when ROP 10 is
completed.
● that ROP 5 and ROP 13 are only started when ROP 10 and ROP 6 are completed.
Image 10-3
SIMATIC BATCH V8.2
Operating Manual, 02/2016, A5E35958174-AA
Non-blocking synchronization point
BATCH Recipe Editor
10.3 Recipe topology
509