Preparing Es Data For Simatic Batch; Pcs 7 - Change Project Type - Siemens SIMATIC BATCH Operating Manual

Process control system pcs 7
Table of Contents

Advertisement

Rational engineering
8.3 Multiproject engineering
Procedure
1. Switch to the plant view using the menu command View > Plant View.
2. Select the multiproject folder and select the shortcut menu command Plant Hierarchy >
Import process cell.
3. Follow the instructions in the subsequent dialogs.
Result
You have imported a remote process cell into your S7 multiproject.
Additional information

Preparing ES data for SIMATIC BATCH

8.3.3
Preparing ES data for SIMATIC BATCH
Introduction
All information available in the ES from imported remote process cells is prepared for SIMATIC
BATCH in the BATCH configuration dialog.
Functions in the BATCH configuration dialog
● The ES data are written to the EQM file using the "Generate" and "Compile" functions in
the BATCH configuration dialog.
● The ES data are copied to the corresponding project directory of Batch with the "Download"
function.
● The ES data are transferred to the SIMATIC BATCH database using the "Update process
cell" action in the BATCH Control Center (BCC).
Additional information
Selecting types of locations for transfer parameters (Page 576)
8.3.4

PCS 7 - change project type

PCS 7 change project type
If you want to insert a PCS 7 project in a PCS & multiproject, you should work in the SIMATIC
Manager with the STEP 7 Master Data Library, to ensure consistency relative to the AS blocks.
A description of how to create a Master Data Library within a multiproject is available in the
online help in the SIMATIC Manager in the chapter "Using the Master Data Library".