Installing a PTX5000 High Capacity Wye AC PDU

Copyright © 2017, Juniper Networks, Inc.

Figure 226: Removing a High Capacity Wye AC PDU

To install a High Capacity Wye AC PDU:
Ensure that the voltage across the AC power source is 0 V and that there is no chance
1.
that the voltage might become active during installation.
Move the power switch located on the faceplate of the PDU to the standby ( )
2.
position.
Grasping both the front and top installation handles, insert the replacement PDU into
3.
the PDU slot. See
Figure 227 on page
Chapter 27: Removing and Installing Power System Components
356.