System-stopped/hot addition (HDD/SSD)
System-stopped/hot addition can be performed on an HDD/SSD. Perform the
following procedure to add the unit.
Figure 7-8     System-Stopped/Hot Addition Flow (HDD/SSD)
1. Opening the rack door
2. Switching the mode switch on the operation
panel to Service mode
3. Checking the operating condition of the
system and the I/O device usage status
4. Stopping the system
5. Adding an HDD/SSD
6. Performing a diagnosis test
7. Confirming that there is no problem with the
installed FRU
8. Returning the mode switch on the operation
panel to Locked mode
9. Starting the system
10. Closing the rack door
108
Fujitsu SPARC M12-1 Service Manual • January 2023
Addition complete

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the Fujitsu SPARC M12-1 and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents