Servicing the Factory Installed PCIe NVMe Switch Card
Note -
the disk backplane area.
7.
Prepare the server for operation.
See
"Prepare the Server for Operation" on page
Servicing the Factory Installed PCIe NVMe Switch Card
This section provides procedures replacing the NVMe Switch card and cables.
For overview information on the factory installed PCIe NVMe Switch card, see
Subsystem" on page
"Component Serviceability, Locations, and Designations" on page
"Replace the NVMe Switch Card (FRU)" on page 213
■
"Replace the NVMe Switch Card Cables (FRU)" on page 215
■
212
Oracle Server X5-4 Service Manual • December 2015
Any excess cable length should be in the PCIe card area to allow better air flow through
30. For serviceability information related to this component, see
259.
69.