Power On the Server

If you removed power from the server during maintenance, use the following procedure to
reapply main power for all server components.
1.
Verify that the power cords are connected to the server and that standby power
is on.
Shortly after AC power cords are plugged into the server, the SP OK indicator blinks as the
service processor boots.
The SP OK indicator is illuminated solid green when the service processor has successfully
booted.
After the service processor has booted, the System OK indicator on the front panel begins
flashing slowly, indicating that the host is in standby power mode.
2.
Press and release the recessed Power button on the server front panel.
When full power is applied to the server, the System OK indicator begins to blink more
quickly as the system begins the boot process.
During the boot process, the server initiates a power-on self-test (POST) which might take
several minutes to complete.
Once the host boot process is complete, the System OK indicator and lights solidly.
Callout
1
2
3
Description
System OK indicator
Power Button
SP OK indicator
Power On the Server
Returning the Server to Operation