6) Connect the power supply plug of the finisher.
(Perform only for EUR)
F-2-26
7) For Finisher /Saddle Finisher , connect the power
supply cable to the host machine. (Perform only
for EUR)
- 1 screw (bind; M4X8) [2]
F-2-27
8) Plug the power supply cable of the machine in the
power outlet.
9) Turn on the power switch on the finisher, and then
turn on the host machine.
10) Enter the service mode and set the connection
sequence.
Choose the item with "Finisher" displayed from
COPIER>OPTION>ACCPST-D>ACC1 to 8 to
enter the connection sequence of the finisher.
MEMO:
When connecting to the host machine directly,
enter "1" and press "OK".
11) Follow the shutdown sequence to turn off the
power switch of the host machine/finisher.
12) Turn on the power switch of the finisher and then
that of the host machine.
2-10
[1]
After setting the connection sequence, the host
machine should be turned off and on to enable the
setting.
Power-On Order for Turning On the
Power When Pickup/Delivery Accessories
are Connected
Be sure to turn on the power in the correct
order otherwise it may cause an error because
the host machine fails to recognize accessories
including this equipment.
[2]
<Power-On Order>
1) Accessories (accessories including this
[1]
equipment)
2) Host machine
MEMO:
There is no power-on order among accessories
Points to Note When Turning Off the
Main Power of the Host Machine
Be sure to turn off the main power in the
following order to protect hard disk of the host
machine.
1) Press the power switch on control panel for
3 sec or more.
2) Follow the instruction on the shutdown
sequence screen (the main power switch will
go off automatically).
3) Turn off the breaker.