Figure 3-34 Installing a power module on the USG9520
Step 12 Verify that the new power module is working normally.
After inserting the power module into the chassis, switch on the air circuit breaker on the
power distribution cabinet and then switch on the power module. Then, you can check the
new power module in the following ways:
l
l
<sysname> display device
USG9520's Device status:
Slot #
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
1
2
3
4
5
6
7
8
9
10
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
The preceding output also indicates that the power module has returned to the normal state. If
the power module is not working normally, contact a local Huawei office for technical
support.
----End
Issue 03 (2017-12-15)
Check the RUN indicator on the panel of the power module. If it is green, the power
module is working normally.
Check the ALM indicator on the panel of the power module, If it is red, the power
module is not working normally.
Run the display device command on the console interface to check the running status of
the new power module. If the power module is working normally, the following is
displayed:
Type
Online
SPU
Present
SPU
Present
LPU
Present
MPU
Present
MPU
Present
CLK
Present
CLK
Present
PWR
Present
PWR
Present
FAN
Present
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Register
Status
Registered
Normal
Registered
Normal
Registered
Normal
NA
Normal
Registered
Normal
Registered
Normal
Registered
Normal
Registered
Normal
Registered
Normal
Registered
Normal
3 Hardware Maintenance
Primary
NA
NA
NA
Master
Slave
Master
Slave
NA
NA
NA
390

Advertisement

Table of Contents
loading

This manual is also suitable for:

Usg9520Usg9560Usg9580V300r001V500r001

Table of Contents